8 free, exam-style Professional Scrum Master I (PSM I) (PSM-I) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free PSM-I practice test to study every exam domain.
These 8 free PSM-I questions are organized by exam domain, so you can see how each part of the Professional Scrum Master I (PSM I) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Understanding and Applying the Scrum Framework
Question 1
Which of the following is NOT a Scrum Value?
- Commitment
- Transparency
- Focus
- Courage
Show answer & explanation
Correct answer: B - Transparency
Question 2
The Product Owner insists the Developers must complete 15 Product Backlog items this Sprint. The Developers believe they can only complete 10. What should happen?
- The team compromises at 12 items to balance both perspectives
- The Developers decide because the number of items selected is their discretion
- The Scrum Master decides based on historical team velocity data
- The Product Owner's decision is final because they are accountable for value
Show answer & explanation
Correct answer: B - The Developers decide because the number of items selected is their discretion
Question 3
A colleague says: 'The Scrum Master is a servant-leader who removes impediments and runs the Daily Scrum with three questions.' How many outdated 2017 concepts are in this statement?
- One - only the three-question format for the Daily Scrum was removed from the Guide
- Two - the servant-leader terminology and the three-question format are both outdated
- Three - the servant-leader label, the impediment removal phrasing, and the three-question format
- Four - all three above plus the assumption that the SM must attend the Daily Scrum
Show answer & explanation
Correct answer: C - Three - the servant-leader label, the impediment removal phrasing, and the three-question format
Domain 2: Developing People and Teams
Question 4
The Scrum Master is sick and cannot attend today's Daily Scrum. What should happen?
- The Daily Scrum is cancelled until the SM can attend
- The Daily Scrum still takes place because it belongs to the Developers
- The Product Owner facilitates the Daily Scrum in the SM's absence
- The team waits until the Scrum Master returns to resume Daily Scrums
Show answer & explanation
Correct answer: B - The Daily Scrum still takes place because it belongs to the Developers
Question 5
A Developer asks the Scrum Master: 'What should I work on next?' The SM's BEST coaching response is:
- Check the Sprint Backlog and assign the Developer a specific task to work on next
- 'What does the Sprint Backlog tell you? What would help progress toward the Sprint Goal?'
- 'I will check with the Product Owner on priorities and get back to you shortly'
- 'Pick whatever task from the Sprint Backlog feels most interesting to you right now'
Show answer & explanation
Correct answer: B - 'What does the Sprint Backlog tell you? What would help progress toward the Sprint Goal?'
Question 6
The Product Owner wants to change the Sprint Goal mid-Sprint due to a market shift. The SM should:
- Allow the Sprint Goal change and adjust the Sprint Backlog to reflect the new direction
- Explain that the Sprint Goal is fixed, and if obsolete, the PO may cancel the Sprint
- Facilitate a team discussion to determine whether the current goal can accommodate the shift
- Renegotiate the Sprint Goal with the full Scrum Team to incorporate the market shift
Show answer & explanation
Correct answer: B - Explain that the Sprint Goal is fixed, and if obsolete, the PO may cancel the Sprint
Domain 3: Managing Products with Agility
Question 7
A Product Backlog item has met its acceptance criteria but does not meet the Definition of Done. Is it 'Done'?
- Yes, because acceptance criteria define completeness for individual backlog items
- No, because both acceptance criteria and the Definition of Done must be satisfied
- It depends on whether the Product Owner accepts it during the Sprint Review
- It is considered Done for the Sprint but excluded from the release Increment
Show answer & explanation
Correct answer: B - No, because both acceptance criteria and the Definition of Done must be satisfied
Question 8
A Product Backlog item that does not meet the Definition of Done at the end of the Sprint:
- Is included in the Increment with a note that it is incomplete
- Returns to the Product Backlog and cannot be released or presented at the Sprint Review
- Is automatically moved to the next Sprint as an inherited commitment
- Is discarded and must be re-created if the work is still needed
Show answer & explanation
Correct answer: B - Returns to the Product Backlog and cannot be released or presented at the Sprint Review
The rest of the PSM-I blueprint
The PSM-I exam also covers these domains. Drill them in the full free practice test:
- Domain 4: Developing and Delivering Products Professionally
- Domain 5: Evolving the Agile Organization